three million ton per year Pellet Plant based on Lurgi Straight
Grate process was commissioned at Mangalore in 1987.
Later on the capacity is increased to four million ton per year. |
![]() |
|
The sized pellets are fed to an indurating machine of 492 M2 grate area through a double deck roller screen to remove undersized and oversized material. The green pellets are dried, preheated, fired at high temperatures and cooled in the indurating machine. The pellets, after screening to remove the undersized material, are conveyed to the storage yard. |
|
Home : Profile : Mining & Benefication : Pelletisation : Products : Port facilities : Quality control : Share Holding : Environment : The Road Ahead: KISCO : Financial Results : Board of Directors : Purchase Tender : Work / Construction Tender : Markets : Pelletisation Process : Concentrate : Pellets : ISO-9001 Certification : Ecology Measures :Top Management : Caring Arm : Our Environment Policy : Contact us :